Progress Report - October 2026

Having spent some time over the summer gaining an understanding of how the original building was constructed, and how we intend to re-create it, the new stonemasons have now started construction work in earnest. Most of the work at present is on the station forecourt side, so you’ll need to get off the train and walk around the back of the building if you wish to inspect progress!

The forecourt side of the building - 30-September-2026 - Photo: F Dumbleton

As well as building up the walls between the windows to the decorative dressed stringer layer, a great deal of work has been undertaken to identify missing stones and also stones which have deteriorated too badly for re-use. In due course Frank, our volunteer architect will have to draw diagrams for any replacement stones required, so that they can be manufactured off-site.

The forecourt / London end corner  of the building - 02-October-2026 - Photo: F Dumbleton

The volunteer team has been working to move much of the remaining stone up to the building site. Our aim at present is to leave only the lintels, cornice stones and bay window jambs and mullions alongside the main demonstration line by the time Santa visits.

We started by moving the remaining coursing stones followed by stones for the stringer layer, and the components of the porch.

Two of the five stonemasons, Matt and John, (John’s left hand is resting where the stringer course mentioned above, will sit) - 9-October-2026 - Photo: T Part

Another two of the five stonemasons, Simon and Steve - 16-October-2026 - Photo: F Dumbleton